Completion of Mochovce NPP continues at a very moderate pace

The latest data show that the third nuclear block is finished to 95.8% and the fourth to 84.2%.
Atómová elektráreň Mochovce
Pohľad na areál Atómovej elektrárne Mochovce SITA

The latest data show that the third nuclear block is finished to 95.8% and the fourth to 84.2%.

The completion of the third and fourth block of the nuclear power plant Mochovce has made a moderate progress. Slovenske Elektrarne, the company in charge of this project, is finishing particularly the third block which is expected to be finalized a year earlier than the fourth one. The latest data show that the third nuclear block is finished to 95.8% while it was 95.4% in summer. More work has been done at the fourth nuclear block over the past months. While this block was completed to 83.5% in summer, it was 84.2% at the end of September. This project has required almost 72 million man-hours.

Full story in Slovak: Dostavba Mochoviec pokračuje. Vo veľmi miernom tempe.

Firmy a inštitúcie: SE Slovenské elektrárne

Odporúčané